黄色大片免费在线观看,国产免费啪啪,在线亚洲欧洲,91视频男人的天堂,日韩在线播放一区,一级特黄录像播放,综合久久91

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學(xué)習(xí) 培訓(xùn)課程
試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(7)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(7)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

You are working on a complex procurement. You must reach agreement with the seller about numerous items including responsibilities and authorities, applicable terms and conditions, contract financing, technical and business management approaches, and price before signing the contract. You scheduled a negotiation session. The seller will have eight representatives at the session; you will have ten. Because this procurement is so complex, contract negotiation should be handled—
A、By an outside facilitator
B、Through alternative dispute resolution procedures
C、As an independent process with specific input and output
D、By establishing a partnering agreement with the seller


相關(guān)試題

推薦文章
合作網(wǎng)站內(nèi)容