After project starts, a senior stakeholder requests that another deliverable be added. The project sponsor previously stated that no further funding would be available for this project. What should project manager do?
A、Ask the project team make a joint agreement to ask for more funding
B、Present the projects scope statement and reject the new request
C、Reject the new request to stop any further information gathering
D、Ask for a formal change request containing all required information