黄色大片免费在线观看,国产免费啪啪,在线亚洲欧洲,91视频男人的天堂,日韩在线播放一区,一级特黄录像播放,综合久久91

軟題庫 移動(dòng)APP 掃碼下載APP 隨時(shí)隨地移動(dòng)學(xué)習(xí) 培訓(xùn)課程
試卷名稱 2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(6)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(6)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

The project manager has just received a change from the customer that does not affect the project schedule and is easy to complete. What should the project manager do FIRST?
A、Make the change happen as soon as possible.
B、Contact the project sponsor for permission.
C、Go to the change control board.
D、Evaluate the other components of the "triple constraint."


相關(guān)試題

推薦文章