黄色大片免费在线观看,国产免费啪啪,在线亚洲欧洲,91视频男人的天堂,日韩在线播放一区,一级特黄录像播放,综合久久91

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學(xué)習(xí) 培訓(xùn)課程
試卷名稱 2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(6)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(6)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

Due to external impacts,the project is canceled by the steering committee at an SPI of 0. 5. what should the project manager do next?
A、Perform an EVA to find whether the CV or the SV is the reason for the SPI of 0. 5
B、Proceed with closure process to transfer the project’s finished and unfinished deliverable to others
C、Nothing,when the project is officially closed by the steering committee, no closure processes required.
D、Conduct a root cause analysis to find the reasons for the cancellation of the project


相關(guān)試題

推薦文章
合作網(wǎng)站內(nèi)容