黄色大片免费在线观看,国产免费啪啪,在线亚洲欧洲,91视频男人的天堂,日韩在线播放一区,一级特黄录像播放,综合久久91

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學(xué)習(xí) 培訓(xùn)課程
試卷名稱 2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(6)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(6)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

uring a project review meeting, the project team member working on activity AD advises the project manager that it will take three more days to complete the activity. The organization's senior manager asks the project manager to find ways to deliver the project according to the original baseline plan, even though it may need additional budget. What should the project manager use to meet the senior manager's needs?

A、Use fast tracking

B、Use fast crashing

C、Apply critical chain methodology

D、Apply leads and lags


相關(guān)試題

推薦文章
合作網(wǎng)站內(nèi)容