黄色大片免费在线观看,国产免费啪啪,在线亚洲欧洲,91视频男人的天堂,日韩在线播放一区,一级特黄录像播放,综合久久91

軟題庫 移動(dòng)APP 掃碼下載APP 隨時(shí)隨地移動(dòng)學(xué)習(xí) 培訓(xùn)課程
試卷名稱 2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(4)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(4)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

A project manager discovers a key feature of the deliverable deviates from the customer’s original specification, but meets quality and legal requirements With budget and schedule constraints team members suggest keeping the original design. White other team members insist on modifying the design to meet the customer’s requirement. After negotiation, the final decision is to keep the current design.The project manager should take which of the following actions next?
A、Follow the risk response matrix
B、Change the quality plan
C、Update scope management plan
D、Follow the change management procedure


相關(guān)試題

推薦文章
合作網(wǎng)站內(nèi)容