黄色大片免费在线观看,国产免费啪啪,在线亚洲欧洲,91视频男人的天堂,日韩在线播放一区,一级特黄录像播放,综合久久91

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學(xué)習(xí) 培訓(xùn)課程
試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(3)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(3)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

A project manager presents the project plan to key stakeholders, citers stakeholder input, and obtains approvals. Later, a stakeholder says that a detail in the communications plan reeds to be changed, The project manager discusses it with stakeholder and they agree to the suggested changes.What should the project manager do next?
A、Create subsidiary documents in the communications management plan.
B、Generate a change request and submit it to the change control board.
C、Keep the project plan as it has been approved by stakeholders.
D、Change the communications plan and request stakeholders’ approval.


相關(guān)試題

推薦文章
合作網(wǎng)站內(nèi)容