The project manager of chain of stores is considering opening a new store in either location A or location B. The project manager delivered the following information.Project location A: payback period is 18 months, NPV is -250.Project location B: payback period is 24 months, NPV is 300.Which project would be recommended to the selection committee by the project manager?
A、Project location A, because the payback period is shorter than the payback for project location  
B、B Project location B, because it’s NPV is a positive number
C、Project location A, because it’s NPV is a negative number
D、Project location B, because it’s payback period is greater than the payback period