試卷名稱 信息系統(tǒng)項目管理師-pmp練習(xí)題-2
考試中心《信息系統(tǒng)項目管理師-pmp練習(xí)題-2》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

During the project performance is reviewed, the project manager identifies some activities that cannot be completed on time, because of poor team performance. What would be next step ?
A、Offer rewards for team members willing to work overtime to meet project needs.
B、 Look for root causes that may be affecting team performance.
C、 Review the schedule to align it to current team performance.
D、 Promise training sessions to increase team performance.