黄色大片免费在线观看,国产免费啪啪,在线亚洲欧洲,91视频男人的天堂,日韩在线播放一区,一级特黄录像播放,综合久久91

軟題庫(kù) 移動(dòng)APP 掃碼下載APP 隨時(shí)隨地移動(dòng)學(xué)習(xí) 培訓(xùn)課程
試卷名稱 信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-2
考試中心《信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-2》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

A project is near completion and a team member report to project manager that there is an issue which will impact an important deadline. The weekly status report will be sent tomorrow to the major stakeholders. What should the project manager do next step?
A、Update the issue log, inform the sponsor, and use escalation process to report a possible delay to the stakeholders.
B、Inform the stakeholder in the weekly status report, discuss possible solutions with the stakeholders and request budget and schedule extensions.
C、Verify if this issue is in the risk plan, if it is not, include it and develop a mitigation plan.
D、Update the issue log, involve all the people that can help to solve the issue, and communicate the issue to the stakeholders.


相關(guān)試題

推薦文章