試卷名稱 信息安全工程師英語試題匯總
考試中心《信息安全工程師英語試題匯總》在線考試
試卷年份2016年下半年
試題題型【單選題】
試題內(nèi)容

When reviewing a project where quality is a major concern, an IS auditor should use the project management triangle to explain that: 
A、increases in quality can be achieved, even if resource allocation is decreased. 
B、increases in quality are only achieved if resource allocation is increased. 
C、decreases in delivery time can be achieved, even if resource allocation is decreased. 
D、decreases in delivery time can only be achieved if quality is decreased. 