An IS auditor noted that an organization had adequate business continuity plans (BCPs) for each individual process, but no comprehensive BCP. Which would be the BEST course of action for the IS auditor?
A、Recommend that an additional comprehensive BCP be developed.
B、Determine whether the BCPs are consistent.
C、Accept the BCPs as written.
D、Recommend the creation of a single BCP.