An IS auditor conducting a review of disaster recovery planning (DRP) at a financial processing organization has discovered the following:
The existing disaster recovery plan was compiled two years earlier by a systems analyst in the organization's IT department using transaction flow projections from the operations department.
The plan was presented to the deputy CEO for approval and formal issue, but it is still awaiting his/her attention.
The plan has never been updated, tested or circulated to key management and staff, though interviews show that each would know what action to take for its area in the event of a disruptive incident.
The basis of an organization's disaster recovery plan is to reestablish live processing at an alternative site where a similar, but not identical, hardware configuration is already established. An IS auditor should:
A、take no action as the lack of a current plan is the only significant finding.
B、recommend that the hardware configuration at each site is identical.
C、perform a review to verify that the second configuration can support live processing.
D、report that the financial expenditure on the alternative site is wasted without an effective plan.
10年專注信管,信管教育專注者,信管網(wǎng)優(yōu)勢(shì)
免費(fèi)試聽信管網(wǎng)信息系統(tǒng)項(xiàng)目管理師課程
全國(guó)前50名高分學(xué)員訪談:董麗(174)、李思...
信息系統(tǒng)項(xiàng)目管理師高端班培訓(xùn)課程
信管老師100小時(shí)直播課程
軟考報(bào)名專題(報(bào)名時(shí)間、入口等)
中級(jí)系統(tǒng)集成項(xiàng)目管理工程師通關(guān)課程
系統(tǒng)規(guī)劃與管理師課程(考試介紹與題型分析)
軟題庫(kù):軟考在線題庫(kù)、支持手機(jī)答題