PMP?當(dāng)天每日一練試題地址:www.jycxcx.com/exam/ExamDay.aspx?t1=33
往期PMP?每日一練試題匯總:www.jycxcx.com/class/27/e33_1.html
PMP?每日一練試題(2023/1/28)在線測試:www.jycxcx.com/exam/ExamDay.aspx?t1=33&day=2023/1/28
點擊查看:更多PMP?習(xí)題與指導(dǎo)
PMP?每日一練試題內(nèi)容(2023/1/28)
試題1
采購部門要求項目經(jīng)理提供一個項目的采購文件.這些文件中應(yīng)包含哪些內(nèi)容?查看答案
試題參考答案:D
試題2
While inviting a transition project to create service for a large company,a project manager discovers that there are multiple business areas with competing requirements.What should the project manager do to obtain consensus among stakeholders?查看答案
試題參考答案:A
試題解析與討論:www.jycxcx.com/st/479595822.html
試題3
—家全球性公司正處于部署一項產(chǎn)品的項目中途。然而,該產(chǎn)品的制造商發(fā)布了一個新版本。新版本必須安裝在任何新部署的產(chǎn)品上。該產(chǎn)品的一個關(guān)鍵部件未在新版本上測試。公司希望在10月31日之前,趕在假日購物季時,在所有門店推出這項新產(chǎn)品。額外的測試會將項目的最終完成日期推遲一個月。項目經(jīng)理應(yīng)該怎么做?查看答案
試題參考答案:B
試題4
在項目執(zhí)行階段.項目經(jīng)理發(fā)現(xiàn)工作分解結(jié)構(gòu)(WBS)中遺漏一個工作包項目經(jīng)理應(yīng)該怎么做?查看答案
試題參考答案:C
試題5
A customer has given you a procurement statement of work f or a complex,eight-month project that has a few unknowns.T he customer has asked you to just"get it done” and only wan ts to see you at the end of eight months when you deliver the finished project.Under these circumstance.which of the following is the BEST thing to do?查看答案
試題參考答案:A
試題解析與討論:www.jycxcx.com/st/476191896.html
試題6
A project requires specialized technical expertise from the engineering.department.However the senior engineer is leading a team on separate pro1ect,and the only available resource is an entry-level engineer.The senior engineer is highly regarded by the customer and the preferred by the project manager. What should the project manager do first to obtain the senior engineer's participation in this project?查看答案
試題參考答案:C
試題7
The project manager is reorganizing a team to develop a new product.The company's technology experts reviewed the standard,and expresses concern that the quality of the product can only be test the new product's new function in system testing phase.This could cause potential schedule and budget delays.What should the project manager do upon learning this information?查看答案
試題參考答案:D
試題解析與討論:www.jycxcx.com/st/491835126.html
試題8
After identifying the occurrence of a risk with a negative impact to the project's budget ,a project manager needs to deter mine if the remaining contingency allowance is enough. what tool or technique should be used?()查看答案
試題參考答案:A
試題9
合同進(jìn)入收尾階段,已經(jīng)完成了審計,下一步應(yīng)該()。查看答案
試題參考答案:A
試題解析與討論:www.jycxcx.com/st/490667666.html
試題10
項目經(jīng)理收到一個新項目的已批準(zhǔn)項目章程。項目章程授予了哪項職權(quán)?查看答案
試題參考答案:C
信管網(wǎng)訂閱號
信管網(wǎng)視頻號
信管網(wǎng)抖音號
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請以權(quán)威部門公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點,為學(xué)員考試保駕護(hù)航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
發(fā)表評論 查看完整評論 | |